According to the Environmental Impact Assessment Law of the People's Republic of China, the State Council Order No. 682 "Regulations on the Management of Environmental Protection for Construction Projects", and the requirements of the Ministry of Ecology and Environment Order No. 4 "Measures for Public Participation in Environmental Impact Assessment", the relevant information about the relocation project of Taiqian County's garbage treatment plant is now publicly disclosed as follows:
1、 Basic information of the construction project
Construction Project Name: Ningbo Bosite Polymer Material Technology Co., Ltd. Thermoplastic Elastomer
Construction nature: relocation
Construction location: West side of Haifa Road, Binhai Industrial Park, Xiangshan County
Construction Content and Production Scale: Ningbo Bosite Polymer Material Technology Co., Ltd. leases Ningbo Xiangtai Machinery Co., Ltd.'s No.1, No.2, and office buildings located on the west side of Haifa Road in Binhai Industrial Park, Xiangshan County. Ningbo Bosite Polymer Material Technology Co., Ltd. has a thermoplastic elastomer production project. The production capacity and main production processes of this project remain unchanged after relocation, and the original factory area will no longer produce after relocation.
2、 Name and contact information of the construction unit
Construction unit: Ningbo Bosite Polymer Material Technology Co., Ltd
Mailing Address: West Side of Haifa Road, Binhai Industrial Park, Xiangshan County
Contact person: Shi Yixiong Contact phone number: 1377171012
3、 Overview of Environmental Impact Assessment Institutions Undertaking Assessment Work
Environmental Impact Agency Name: Zhejiang Renxin Environmental Science Institute Co., Ltd
Unit address: Building 3, Shuijie, West Business District, South of Rili Middle Road, Yinzhou District, Ningbo City
Contact person: Lin Gong Contact phone number: 0574-65760080
4、 The working procedures and main work contents of environmental impact assessment
This environmental impact assessment work is carried out in accordance with national regulations such as the Technical Guidelines for Environmental Impact Assessment and the Environmental Impact Assessment Law of the People's Republic of China. The main content of this evaluation is: project overview and engineering analysis, review of pollution prevention and control measures, environmental impact prediction and evaluation, etc.
5、 Main matters for soliciting public opinion
Based on the brief introduction of the construction location and content of this project, solicit opinions from the public and relevant units on the project construction. If you have any questions, please call the consultation hotline.
Scope: Main villages, schools, government agencies, enterprises and institutions around the project location.
Time: Within 10 working days from the date of this announcement.
6、 Online link to public opinion form
Public opinion form online download link: http://www.zjzwfw.gov.cn/
7、 The main ways for the public to express their opinions
During the process of soliciting opinions on the environmental impact report form, the public can provide opinions related to environmental impact assessment to the construction unit. The public can submit the completed public opinion form, etc. to the construction unit within the specified time through letters and emails, reflecting opinions and suggestions related to the environmental impact of the construction project.
1. Announcement time: Ten working days from May 6, 2019;
2. The starting and ending time for public opinions: ten working days from May 6, 2019.